Skip to main content

Use Cases

UK Working Day Use Cases

Worked examples showing how dates, public holidays, court closures and boundary settings change a count. For help setting up the controls, see the calculator guide. For deeper guides and edge cases, browse Articles.

Conveyancing Professional:

Model an SCS Notice to Complete Period

Scenario

Assume an England and Wales residential contract incorporates the Standard Conditions of Sale (5th edition, 2018 revision) without changing the relevant provisions, and a notice is established as given on 17 December 2026. Condition 6.8.2 provides for completion within ten working days, excluding the notice day. This example models that period only; the contract and transaction facts must establish whether the notice mechanism applies and when the notice was given.

Calculator configured for a ten-working-day England and Wales notice period
Tap to enlarge

Example Workflow

Use the step row to inspect each part of the workflow.

8 steps

Step 1

Deadline

Select Deadline in Default Mode

Result Example

Notice given: Thursday 17 December 2026 (excluded)
Tenth working day: Tuesday 5 January 2027 (included)
Public holidays excluded: Christmas Day, observed Boxing Day, and New Year's Day
The result is a mechanical count from stated contractual inputs. It does not establish that the notice was valid, available, or received on the date entered.
Calculator result showing ten working days from 17 December 2026 ending on 5 January 2027
Tap to enlarge

Why This Matters

  • Model a verified contractual period without treating it as a universal rule
  • Apply the England and Wales bank holidays
  • Show exactly which weekends and holidays were excluded
  • Save a reproducible record of the calculator inputs
  • Change the inputs when the signed contract varies the standard conditions

Litigation Solicitor:

CPR Notice – 3 Clear Days for an Interim Application

Scenario

Assume an interim application hearing in the High Court of England and Wales is listed for Tuesday 14 January 2025 and CPR 23.7(1)(b)'s three-clear-day period applies. Court Rules Mode counts backwards using the CPR boundary and short-period rules. The user must still confirm the hearing date, service method, and rule that applies.

Calculator setup for CPR notice scenario
Tap to enlarge

Example Workflow

Use the step row to inspect each part of the workflow.

6 steps

Step 1

Court Rules

Select Court Rules

Result Example

The calculator counts backwards from Tuesday 14 January 2025 and excludes both the service date and the hearing date. Because the period is 5 days or fewer, CPR 2.8 applies working days only:
Day 3: Monday 13 January 2025 (working day)
Day 2: Friday 10 January 2025 (working day)
Day 1: Thursday 9 January 2025 (working day)
Latest compliant service date: Wednesday 8 January 2025.
Court Rules Mode shows the profile and excluded days used in the count.
Calculator result for CPR notice period
Tap to enlarge

Why This Matters

  • Apply the 3 clear days requirement without hand counting
  • Avoid miscounting weekends or bank holidays when working to CPR Part 23
  • Show the calculated service date and the days left out
  • Keep the hearing date, court profile, and period visible for checking

Scottish Litigation:

SCTS Filing Deadline Across the Easter Court Closures

Scenario

Assume a Court of Session timetable gives ten days from a start date of 10 April 2025. The Judicial Office closure dates and Scottish bank holidays cover the Easter period. This example shows the resulting date; it does not decide the correct start date or period for a case.

Calculator setup for Scottish court filing scenario
Tap to enlarge

Example Workflow

Use the step row to inspect each part of the workflow.

7 steps

Step 1

Court Rules

Select Court Rules

Result Example

Starting from 10 April 2025, the ten-day count lands on Sunday 20 April. The selected office is closed over the weekend and on Easter Monday, so the result moves to Tuesday 22 April 2025. The result lists the dates used in that adjustment.
Calculator result showing Scottish court closure handling
Tap to enlarge

Why This Matters

  • Use both SCTS closure dates and Scottish bank holidays
  • See when filings roll forward to the next open court day
  • Show the selected SCTS court or office
  • List the closure dates used in the result

Northern Ireland Litigation:

High Court Notice – 5 Clear Days Over the Twelfth Fortnight

Scenario

Assume a High Court of Northern Ireland hearing is listed for Monday 21 July 2025 and the relevant rule requires five clear days' notice. The Battle of the Boyne holiday falls on 14 July in Northern Ireland. Court Rules counts backward using the High Court short-period and clear-day settings.

Calculator setup for Northern Ireland court notice scenario
Tap to enlarge

Example Workflow

Use the step row to inspect each part of the workflow.

7 steps

Step 1

Court Rules

Select Court Rules

Result Example

The calculator counts backwards from Monday 21 July 2025 using clear days (excluding both the service date and the hearing date). Because the period is 7 days or fewer, the NIR High Court rule counts working days only:
Day 5: Friday 18 July (working day)
Day 4: Thursday 17 July (working day)
Day 3: Wednesday 16 July (working day)
Day 2: Tuesday 15 July (working day)
Monday 14 July — Battle of the Boyne (skipped)
Saturday 12 – Sunday 13 July (weekend, skipped)
Day 1: Friday 11 July (working day)
Service Deadline (Excluded): Thursday 10 July 2025.
With the same dates and period, the 14 July holiday makes this result one day earlier than an England and Wales calculation. Check the relevant rule and service requirements before using it.
Calculator result for Northern Ireland High Court notice period
Tap to enlarge

Why This Matters

  • Apply Northern Ireland's bank holidays, including the Twelfth
  • Apply the High Court threshold (≤7 days = working days, clear days)
  • Keep the Northern Ireland court level visible
  • List the dates left out of the count

HR Manager:

Six-Week Statutory Notice Example

Scenario

Assume an employee in England has six complete years of continuous service, the statutory minimum in section 86 of the Employment Rights Act 1996 applies, and notice takes effect after it is given on 28 November 2025. This example counts six calendar weeks. It does not decide whether a longer contractual period applies or whether notice was validly given.

Calculator setup for UK employment notice period
Tap to enlarge

Example Workflow

Use the step row to inspect each part of the workflow.

7 steps

Step 1

Deadline

Select Deadline mode

Result Example

Service Length: 6 years (continuous)
Statutory Notice Entitlement: 6 weeks
Notice Given Date: 28 November 2025 (notice period starts 29 November)
Termination Date: 9 January 2026
The six weeks run as calendar weeks. Christmas Day, Boxing Day, and New Year's Day remain in the count, so they do not extend it. On the assumptions above, the period ends on 9 January 2026. Pay, accrued leave, and the effective termination date still depend on the employment facts and applicable terms.
Calculator result for UK employment termination notice
Tap to enlarge

Why This Matters

  • Counts a supplied six-week period in calendar weeks
  • Shows that weekends and bank holidays remain in the count
  • Keeps the assumed notice date and boundary settings visible
  • Leaves notice entitlement, effective service, pay, and dismissal questions for separate checking

Quantity Surveyor:

Five-Day Construction Payment Notice Period

Scenario

Assume 15 December 2025 is the payment due date under a construction contract and the five-day period in section 110A of the Housing Grants, Construction and Regeneration Act 1996 applies. The Act says the notice must be given no later than five days after the due date. It does not turn those five days into working days or add an industry Christmas shutdown. This example counts that period only.

Calculator setup for a five-day construction payment notice period
Tap to enlarge

Example Workflow

Use the step row to inspect each part of the workflow.

7 steps

Step 1

Deadline

Select Deadline mode

Result Example

Payment due date: Monday 15 December 2025 (excluded)
Five calendar days: 16–20 December 2025
Last day in this count: Saturday 20 December 2025
The weekend does not extend this calendar-day period. Check the contract to confirm the due date, who must give the notice, and how it must be served. A pay-less notice has a different trigger tied to the final date for payment, so it is not modelled as a second fixed period here.
Five calendar days after a construction payment due date
Tap to enlarge

Why This Matters

  • Shows the five-day payment-notice period as a calendar-day count
  • Keeps the due date and boundary choices visible
  • Does not add a Christmas shutdown that the Act does not provide
  • Leaves the contract, notice route, and service requirements for separate checking